Wednesday, March 30, 2011

Subbase preparation

Laying subbase (stabilised layer to C1 quality) at 10+600 Tanga-Horohoro road. Seen in picture are roller, paver, water bouser and grader

Sunday, March 27, 2011

Pile Load Testing

This is an assembly of Pile Load Test by method of "Maintained Load Test" whereby a constant load is maintained until no significant settlements are recorded then a load is changed, and process is repeated till specified load.

Sunday, March 20, 2011

Intro

Hello readers,
You are welcome to participate in this blog, I will keep on writing to you what I think is important concerning Tech, Computer, Software and engineering works.

In short these are my favourites.
So Keep on posting your comments